McCombs
Plaza
Owner: Red McCombs
GC: Koontz - McCombs
Acres: 3
Pad Area: 53,000 SF
Paving Area: 15,700 SF
Located behind the existing Trinity III on Broadway and 281,
McCombs Plaza was built against an existing building which housed
the office of the project architect. The structure, which is
currently McCombs Headquarters, is comprised of a parking garage,
parking lots and a multi-story building. Also included in the
package was site excavation and building backfill. |
| |
|
|
|
Red
McCombs Toyota
Owner: Red McCombs
GC: Koontz - McCombs
Acres: 4
Pad Area: 47,000 SF
Paving Area: 113,000 SF
New construction did not close operation at McCombs Toyota.
Salesman were able to continue to sell cars as M&M put extra
efforts into dust control. The scope included light demolition
of an existing structure and light concrete work along I-10.
M&M was also involved in an extension of a major culvert,
where we provided excavation and backfill services. |
| |
|
|
|
South
Texas Blood & Tissue Center
Owner: South Texas Blood & Tissue Center
GC: Bartlett Cocke General Contractors
Acres: 3.5
Pad Area: 47,000 SF
Paving Area: 113,000 SF
This contract included selective demolition, an extension of
an existing building, and both concrete and asphalt paving. |
|
| |
|
Valero
II
Owner: Valero
GC: Spaw Glass
Paving Area: 80,000 SF
What is now the SAWS headquarters, this facility was a suspended
structure constructed between two existing buildings. During
the pier drilling operation, methane gas was noticed along with
a layer of trash. It was brought to the contractors attention
that the site was used as a city dump prior to the commencement
of the project. Unfortunately, the layer of trash was not discovered
until the majority of the piers had been set. In order to alleviate
the problem and not damage the piers, M&M site crews carefully
excavated the contamination and replaced it with common fill.
Afterwards, crews backfilled around the building and constructed
new paving. |
|
|
| |
| |
|
|
|